Task Report - Procurement Schedule exported to excel

Andrew OwensonMember for 18 years 4 months
Created
1
3
0

Hi Guys

I am using ASTA 12.5.

I have a task report for a procurement schedule which exports to excel. What I need to do is adapt the report to what my company wants to see. The template came with the software, but I cannot work out how the dates are linked to the activities.

Prep Tender Docs Finish Date, Tender out Start date, Tender in Finish date, etc.. mobilisation duration & Free float, start on site Date

 

This is going to be in excel with one package/line with the columns representing the activites.

 

How do I make the table match the activities. Sorry if this is not clear, but I am really frustrated with this software. As a throwaway I would like to add a actual and forecast date for each!

 

Any thoughts

 

Andrew

 

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi AndrewWith which software

    Hi Andrew

    With which software are you frustrated?

    It seems that you have a vertical list from Asta that you want to change into a horizontal list in excell.

    There is a feature in excell that will do this on one click - it ceratinly works in Lotus 123.

    Alternatively you can set up a template on a single sheet where you add + cell address in a horizontal format that automatically links to the vertical data.

    Best regards

    Mike Testro