TIX files

Bijaya BajracharyaMember for 21 years 7 months
Created
2
1
0
In Power project, .pp is the main project file, .bak is the backup, .ppb is the baseline. And there is one more file type .TIX. I want to know what this file is for.

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Bijaya
    TIX files are generated when you exit PowerProject; whatever the size of the project file, TIX files are (always or most of the time?) only 1 kb large; I presume they are some kind of index file
    you can delete them with no problem
    Alexandre
  2. 0
    Bijaya Bajracharya ·
    Thank you.

    I also got reply from ASTA telling me that the .tix file is like a cache file. It saves information when you perform various actions so they are quicker next time you run them. You can delete the tix file but it will be recreated each time you open the project.

Log in or join to reply