Everytime I save asta PP programme copy of BAK file created on the same folder. How do I stop this? Any help appreciated

2 replies

Oldest first
  1. 0
    Ben Taunt ·

    File > Options > Edit Tab >

    File > Options > Edit Tab > Create BAK Files (backups)

    However, if you turn this off you will disable the auto-backup funtionality of Powerproject...  BAK files are used to recover your work in the event of any issues.

    Thanks,

    Ben @ Elecosoft

  2. 0
    Anu H ·

    Many thanks So this means if

    Many thanks So this means if ASTA crashed inthe middle of writing a programme I wont  be able to open it from recent files if I turn this off?