Can anyone advise on how to convert a pp programme into MSP? And just to make it a bit more of a challenge - I have the Asta viewer - not the PP software - can this be done without PP license?

7 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Selina,
    AstaDev has developped their own macros to export PowerProject and MS Project files to XML; as both software apps do READ XML, it is a convenient way to transfer a PP file to MSP and vice versa
    As far as I know, you have to use a full PP to do that, because you will install the macros inside the app.
    You could try downloading PP and trial-testing it during one month
    In case you cannot get the macros, just send me a private mail
    Alexandre
  2. 0
    Andrew Pearce ·
    The other way is if you can get the originator of the PP file to send you the file exported in xml format.
  3. 0
    Alexandre Faulx-Briole ·
    Nope,
    do not forget that PowerProject 8 is using a specific XML format; saving a MS Project plan as a XML file will not work, you HAVE to use AstaDev macros to save and import XML files
    Alexandre
  4. 0
    Shahzad Munawar ·
    I totally agree with Alex that saving in XML format by using PP version 8and opening in MS project may not serve your purpose because by doing that you will lost a lot of data especially colour coding therefore it is advisable to use ASTADE macros first and then import XML file.

  5. 0
    Varun Shinde ·

    I want to export Full loaded

    I want to export Full loaded with Quantity & Cost ASTA PP file to MSP. It this possible to view same quantity & Cost in MSP?? If yes what is d procedure??

  6. 0
    Ben Taunt ·

    Hi Varun,What version of Asta

    Hi Varun,

    What version of Asta Powerproject are you using?  In the latest release, version 13, you can simply save your file to MS Project XML format or now also .mpp if you have MS Project installed alongside Asta Powerproject.

    The help files are full of advice on any differences between how the data is converted so do take a read of those to understand the process best.

    Thanks,

    Ben 

     

     
  7. 0
    Matthew McCombs ·

    Does anyone know how to

    Does anyone know how to convert 2003 Microsoft Project Files into Asta Power project?