Filtering on Predecessors and Successors

Oliver JohnstoneMember for 20 years 7 months
Created
2
3
0
Can anyone tell me how to create a filter which will present the direct predecessors and the direct successors to a particular activity.

Thanks

2 replies

Oldest first
  1. 0
    Mal Leadbetter ·
    Oliver

    From an unfiltered view, click on the activity whose predecessors / successors you wish to see.

    Then go to toolbar, select view. From the drop down menu select view and from the next drop doown menu you should see an option for Predecessors & Successors. Click this and this gives you your direct predecessors and successors

    Knowing (or not as the case maybe) PowerProject, there is probably a shortcut to do the above!

    Hope this helps

    Mal
  2. 0
    Carlos Arana ·
    When inside this P&S view, what’s the quickest way to jump to the pred/suc of one of those activities in the view?