Filtering Formula Columns

Craig McCartneyMember for 11 years 1 month
Created
3
3
0

Hi Guys,

I have created a formula column called ductwork, which simply outputs a 1 if the task name contains the word ductwork and 0 if not. My formula works great, however I would now like to create a filter to hide all 0's in a column, I have tried the filter tab, but it appears it wont let me filter the column. Can anyone offer some advice regarding how I can over come this?

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi CraigTwo options.You can

    Hi Craig

    Two options.

    You can copy paste the results of your formula into a user field and filter on that.

    Just filiter on *Ductwork* in the Names and Titles filter section.

    Best regards

    Mike T.

  2. 0
    Robert Hughes ·

    Hi Craig,Didi you have any

    Hi Craig,

    Didi you have any particular reason for going about it this way?

    As Mike says, you can setup a filter to searh activity titles using the 'Bar/Task title' filter condition which will acheive the same result.

  3. 0
    Craig McCartney ·

    Cheers, there is a fix in

    Cheers, there is a fix in that latest update that allows you to filter formulas with ease.