Site progress

Dave CrosbyMember for 18 years
Created
5
3
0
Is anyone on here using Site Porgress? This allows you to update progress in Powerproject via the web. I would be interested in hearing feedback from anyone who is or has used it.

5 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Dave

    I have never used it although I did buy an early prototype that worked with Task Per Line mode but not very succesfully.

    I do remote progress updates from sites by email.

    The site fills in a spreadsheet with the activities and the percentage column and email it to me and I just cut and paste into the programme.

    Best regards

    Mike Testro
  2. 0
    Dave Crosby ·
    Thanks Mike.
    I hope you weren’t discouraged by an early prototype. No doubt it has come a long way since then. Remote access to the web is so much better than it used to be as well.

    Cheers,

    Dave.
  3. 0
    Ian Watts ·
    Hi Dave

    I use it on three projects and have had great success,saves me a lot of time, the only promlem is site managers progress before the previous task is complete, making the drop line unsure of where to go
  4. 0
    Mike Testro ·
    Hi Ian

    Are you using task per line mode?

    Have you tried setting the reschedule to Link Around Completed tasks?

    Best regards

    Mike Testro
  5. 0
    Ian Watts ·
    Hi Mike,
    Appreciate the help, can you give me more detail.

    Kind regards

    Ian Watts