Linking Progress

Dean GrimesMember for 14 years 10 months
Created
11
4
0

First post to the forum so please bear with me.

 

I am trying to link % complete on two or three seperate tasks but not having a lot of success.

I want to be able to enter the % complete on one bar but at the same time it enters the same the summary bar then updates another summary bar elsewhere.

 

the reason behind this is that i am running a contract programme and a target programme, however i am only doing the weekly updates against the target programme although i need to show the % complete on the Contract programme.

 

if you can help it would be a great help

 

Dean

11 replies

Oldest first
  1. 0
    Anoon Iimos ·

    how can % complete affect

    how can % complete affect tasks having no relationships?

    you should define logic-links.

  2. 0
    Vladimir Liberzon ·

    Anoon,the question is about

    Anoon,

    the question is about moving actual data from one project version to another.

    I don't know how it is done in Asta, let's wait for the answers of Asta experts.

    Regards,

    Vladimir

     

     

  3. 0
    Anoon Iimos ·

    Vladimir,It's the same

    Vladimir,

    It's the same thing.

    What if the two versions were completely different (i.e. in layouts)?

  4. 0
    Vladimir Liberzon ·

    Anoon,layout does not

    Anoon,

    layout does not matter.

    I don't know how it is done in Asta, in Spider Project actual data of all activities will be imported and project status will be shown in any layout.

    But it is necessary activity and resource codes to be the same in both versions.

  5. 0
    Mike Testro ·

    Hi Dean Welcome to planning

    Hi Dean

    Welcome to planning planet.

    When you enter a percentage progress in a task the value rolls up to the upper level summary bars.

    You can switch this off in the progress column dialogue box by clicking off the rolled up values.

    If you need to enter the same data to two programmes that have the same format and the tasks are in the same sequence then just copy and paste between the columns.

    Best regards

    Mike Testro

  6. 0
    Vladimir Liberzon ·

    Anoon,Mike explained what did

    Anoon,

    Mike explained what did you mean by stating that there is a need in the same layouts. With copy - paste technique it is necessary.

  7. 0
    Mike Testro ·

    Hi Vladimir If the two

    Hi Vladimir

    If the two layouts are different I have developed a method in the spreadsheet to solve the problem.

    The ouput data is in one sheet with unique Task ID's and the input data is in the other sheet with a Vlookup formula that picks up the data with reference to the same Task ID.

    The result is copy paste to the output programme.

    This works best with Lotus 123 and Asta Powerproject.

    Best regards

    Mike Testro

  8. 0
    Vladimir Liberzon ·

    Hi Mike,thank you, I

    Hi Mike,

    thank you, I understood your approach and expect that it is clear to Asta users.

    I expect that by copy-paste you import not only %complete but also all other data including actual and remaining work, actual and remaining duration, actual and remaining material requirements, actual and remaining costs, etc. I hope that Asta does not make all these data proportional to %complete?

    Best Regards,

    Vladimir

  9. 0
    Mike Testro ·

    Hi Vladimir Anything on a

    Hi Vladimir

    Anything on a spreadsheet can be copy pasted into Powerproject and back again.

    Regarding proportionality I really don't know, my work as a delay analyst does not involve day to day project time control.

    Best regards

    Mike Testro

  10. 0
    Anoon Iimos ·

    Hi Mike,It's quite confusing

    Hi Mike,

    It's quite confusing that (you) being the promotor of Finish-to-Start (FS) only, and it seems that you don't care about the day-to-day activities (as a delay analyst)?

    If I remember correctly, you also mentioned that "disruption" starts from "upperfixer" or something (the one who climb the ladder fixing something).

    I agree with Vladimir, copy and paste will only work on exactly the same program (twins).

     

    Kindly enlighten me please?

  11. 0
    Johannes Vandenberg ·

    Hi DeanTo work and update two

    Hi Dean

    To work and update two schedules at the same time is quit common in P6. The main reason is often that variations are already implemented but not yet approved.

    Suggest to proceed as follows;

    • Baseline the schedule, when completed, and call this the "Contract Program" 
    • Note that % completion on duration type can be rolled up to a higher level.
    • Units and Physical % completion cannot be rolled up.
    • As and when it becomes necessary update it with durations, and or labor units.
    • When ready, baseline the schedule and call it "Target Program".

    So, now their are two "Programs" in the same schedule.

    Updating the schedule

    • Update the schedule say on a weekly basis. Their is only one schedule!

    Analysis an reporting

    • Assign the baseline "Contract Program" to the schedule. Note, this is not the same as making or setting the baseline.
    • Now you can apply all the CPI, Performance, Schedule % completion, Schedule Variance you desire against the Contract Baseline. 
    • The next step to assign the Target Program to the schedule and report the against the Target Program.

    Trust this helps

    Johannes

     

     

     

     

Log in or join to reply