Linking Progress
In the Open Standard
Dean GrimesMember for 14 years 10 months
- Created
- 11
- 4
0
First post to the forum so please bear with me.
I am trying to link % complete on two or three seperate tasks but not having a lot of success.
I want to be able to enter the % complete on one bar but at the same time it enters the same the summary bar then updates another summary bar elsewhere.
the reason behind this is that i am running a contract programme and a target programme, however i am only doing the weekly updates against the target programme although i need to show the % complete on the Contract programme.
if you can help it would be a great help
Dean
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?