We have been asked by our client to intergrate our Project Management Software with SAP and to provide a FTPS export with defined fields.

We currently use Asta Powerproject for our project management. Does anyone have any knowledge / experience interfacing SAP with Asta?

Thanks

Gavin

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Gavin

    I have had no experience of SAP software but you can copy and paste any data from the columns to any spreadsheet and make whatever use of it you wish.

    Contact Asta Support and they will tell you - their website seems to be down at present.

    Best regards

    Mike Testro
  2. 0
    Gavin Clegg ·
    Thanks Mike,

    I have been trawling the web and forums for any information. I have already made contact with the chaps at Asta but just thought anyone out there had any experience / pitfalls etc.

    I know P6 has "inspire" which interfaces with SAP but it all looks very expensive and would be probably be underused!! As is my experience with Primavera products.


    Thanks

    Gavin