Power Project Legends

Adam AinsleyMember for 17 years 2 months
Created
1
2
0
Morning all,

Does anyone know how to get the legend on every page of the chart.

Currently i can only get the legend on the very last page of the print out.

Cheers

1 reply

Oldest first
  1. 0
    Mike Testro ·
    Hi Ainsley

    This one is for the wish list in V 11.

    You should contact to Asta Team to get it in the software - same as Lock Dateline to page.

    Meanwhile - instead of using page breaks you can turn each print page into a "project".

    It is a cumbersome solution but the logic will be unchanged.

    Best regards

    Mike Testro