Progress Expert

Kayode OniMember for 19 years 5 months
Created
4
2
0

Has anyone come across a descrepancy btw progress figures in asta pp summary bar & progress expert figures. I have tried to contact Asta Dev, but PE2 is unsupported.

Kayode

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Kayode

    What version are you using - PE2 does not appear on Asta website.

    I have never come across "Progress Expert" in powerproject.

    Best regards

    Mike Testro
  2. 0
    Kayode Oni ·
    Hi Mike,
    Currently use Version 10. PE2 is a standalone application - macro.
    I downloaded this application from Asta dev website.
  3. 0
    Mike Testro ·
    Hi Kayode

    Sorry - I have no experience of this macro so I cannot help you any further.

    Best ignore the conflicting data and stick with the PowerProject summary figures.

    I hope you did not pay too much for the download.

    Best regards

    Mike Testro
  4. 0
    Kayode Oni ·
    Thanks Mike. The download was and is still free!