Baseline Date Columns

Lee MallekMember for 21 years 5 months
Created
2
5
0

Can anyone assist me in displaying baseline start and finish date columns in Powerproject?

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Lee Use the baseline

    Hi Lee

    Use the baseline option to show the bars in there own lines or set up start and end date columns that rela\te to the baseline.

    Best regards

    Mike Testro

  2. 0
    Chris Rymer ·

    The start and end date

    The start and end date columns look at the project data when you first set them up. To point them at a baseline right click on the heading of the column and select Table Definition. Make sure the column you want to amend is selected in the left hand window. In the right hand window the Detail tab will show Live, click into here and select the baseline. This should be repeated for any column that you want to show baseline data.

    Hope this helps

     

    Chris