Week Numbers in columns using user fields?
In the Open Standard
Andrew OwensonMember for 18 years 4 months
- Created
- 8
- 4
0
I need to put the week numbers against activities. ie act 1 starts on the 2nd June. On the calendar I have set 2nd June as week one. How do I have that next the start date of the activity - same with the finish date.
Act Start Wk No. Finish Wk No.
vvvvvvv 02.06.14 1 20.06.14 3
Regards
Andrew