Asta PowerProject - Remove horizontal thick black line

K YongMember for 19 years 11 months
Created
2
1
0

Hi all! Just recevied a sub-con. Asta programme and on the programme they have shown thick horizontal black line to each section. Can't remember how to switch the line off. Any Asta expert here can help? Please see attached print screen of the programme.

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi K Yong This could be the

    Hi K Yong

    This could be the Page Break for printing.

    Select the bar underneath the line and then go to Insert - Page Break - deselect.

    Mike Testro

  2. 0
    Robert Hughes ·

    This may have been

    This may have been resolved by now but i suppose it will be helpful to anyone searching this topic. 

     

    Where there is an unbroken horizontal line like that (i believe a page break is a dashed line?) it is where the ruling line properties have been modified for that bar to be shown thicker / bolder.

     

    Right click on the chart on the bar below the line, press 'Ruling Lines.....' and a small window will open, go to the 'Specifics' tab and double click the box to the right of 'Appearance:' and another window will open, in this window you can change the formatting of the ruling line to match the rest of the chart.