Progress Planned and Achieved by Code
- Created
- 1
- 1
Is it possible to do the following?
I have a construction programme that has builders elements, electrical elements and plumbing elements. The programme has been baselined. I do a dropline each week inputting percentages achieved. This gives me the planned and achieved percentages for the programme as a whole. What I would like is to split out the builders planned and achieved, the electrical planned and achieved and the plumbing planned and achieved. Whilst filtering by code seperates the tasks into the 3 catagories the overall planned and achieved figures remain the same and do not adjust for that particular code.
Any assistance would be appreciated.
Regards
Mike Jackson.