Re-schedule

Ronan NilandMember for 14 years 3 months
Created
4
3
0

After I press F9 to re-schedule a box appears on the screen, asking what date to straighten the progress line to. I turned that box off, and now I want to turn it on again. How do I do this ??

 

Thanks 

 

Ronan

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ronan There are two sets

    Hi Ronan

    There are two sets of adjustments - assuming you are using the Icons and not that horible ribbon.

    1. Tools > Options > Reschedule to set the progres line reschedule date.

    2. Format > Barchart > Progress to turn the line display on or off plus other toggles.

    Best regards

    Mike Testro

  2. 0
    Chris Rymer ·

    RonanTo turn the dialogue box

    Ronan

    To turn the dialogue box back on (in Version 12) go to File - Options - General. On the right hand side is a button called Do not show again prompts.... Click on this and select the Reset button. This will will restore the box you are after.

    Regards

    Chris Rymer

     

  3. 0
    Yasin Vural ·

    Ronan Niland, are you using

    Ronan Niland, are you using v11 or v12? 

  4. 0
    Ronan Niland ·

    V 11

    V 11

Log in or join to reply