I have been given a programme to review. It Asta V12. When I re-schedule, I find 2 tasks that have

  1. No Links (in or out)
  2. No constraints of any kind

After I re-schedule (F9), the tasks “just sit there”. They do not move back to the re-schedule date. I can “move” them to another date, and again they just sit there. What is causing this??

Ronan

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ronan Goto Tools > Options

    Hi Ronan

    Goto Tools > Options > Reschedule and you will see three options for tasks with no links.

    Yours is pobably set to > "Leave as drawn within constraints"

    Choose any of the other two to get a different option - the task will probaly fall back to day 1.

    Best option is to put some logic onto it.

    Best regards

    Mike Testro

  2. 0
    Ronan Niland ·

    Thanks

    Thanks