Staff Resource Planning Using ASTA

Joseph McCluskeyMember for 14 years 3 months
Created
1
2
0

Hi All,

I have been tasked with creating a site staff resource programme by my employer.

I am relatively new to planning and am hoping someone could provide me with suggestions on how to efficiently create a programme for staff resources using ASTA.

The objective of the programme is to view working time against non productive time to assign excess capacity to jobs.

Any assistance would be greatly appreciated.

Thanks

Joe

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Joseph Set up a series of

    Hi Joseph

    Set up a series of task hammocks that contain the scope of work for each staff resource. For instance if you are employing an MEP supervisor then add all the MEP tasks to the hammock and then add the Supervisor resource to the hammock.

    The same with other trades such as Groundworks - concrete - finishings etc.

    Staff that are going to be on site full time add to the project Level 1 summary.

    Best regards

    Mike Testro