Asta Power v11 - Progress line not transferring when imported in P6 v 6.2
In the Open Standard
Emmanuelle PrefolMember for 14 years 10 months
- Created
- 1
- 2
0
While progress line on a programme generated with Asta Power Project (APP) with v11 is @ 10/08/12. When file is saved as Primavera .xer and either re-opened in APP on in P6 V6.2, progress line/data date is changed to 24/03/12 which is actually the start of the project? What I should I be checlking?
Additionally, when programme either re-opened in APP on in P6 V6.2, start of in-progress activities are actualised in 2008/2009 and end dates brought back in?
Any ideas.
1 reply
Oldest firstLog in or join to reply