Hi Ronan
The first thing to do is to take off the software logo.
After that the sky is the limit on what you can put on the Border.
It all depends on who will be looking at the printed page.
An internal reviewer may need to see confidential information such as the author - total float - target date etc
File Path and Version Number are useful information
Whereas the employer would need a different set of information.
I try to keep things simple by using the F9 text key which lifts data from the file and embeds it in the border.
Particularly useful is the View Name which tells the reviewer exactly what is on the chart.
Best regards
Mike Testro