User defined field - not showing unless i put a date on the chart

Christine PMember for 17 years 5 months
Created
3
5
0

Hi there

Made a user defined field via "User Field Manager" called Frequency, all I want to type in there is "Monthly" or "2 yearly" or "Weekly" etc.

I've added it to my chart, I type in the activity description as usual, I type in the "Frequency" column the frequency but when I move off the column onto another, I lose whatever is in the "Frequency" column - unless I draw a date on the gant chart.

I've had this problem before, and Ive sorted it, but that was about 2 year ago and I now cant for the life of me work out how to have whatever is in my user defined columns show up without a dat against it.  Anyone help please!?

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Christine This is an

    Hi Christine

    This is an inherent problem - you can only type data in a user field if there is a task on the bar.

    You can put the information in the  Task Name Column - enter a task - Type The Frequency information - delete the task - not the bar - then you can format the text.

    I hope that helps

    Best regards

    Mike Testro

  2. 0
    Christine P ·

    Thanks Mike! I thought I'd

    Thanks Mike!

    I thought I'd managed it before, perhaps I hadn't after all :D

    No worries, Im putting milestones in as I go along anyway and will be moving them all when Im done so the problem is pretty much sorted - for this time anyway :)

  3. 0
    Ben Taunt ·

    Hi Christine,Mike is correct

    Hi Christine,

    Mike is correct for when your UDF is set up as a Task UDF.  However, if you use a Bar UDF then you should have the functionality you need.

    Ben 

Log in or join to reply