User defined fields?

Christine PMember for 17 years 5 months
Created
2
5
0

Hi all

I have a spreadsheet, with milestone dates on that the boss wants putting into Powerproject.  Theres several headings such as "name", "Value", Status" as well as the dates.

Im trying to make my own user defined fields for the headings.  I have created them under "User Field Manager" and selecting "bar" and "String".  Nno problem there. 

But when I add the columns onto the programme, nothing will appear in the column when I type unless I put in a token bar on the chart side.  How can I make my writing appear please?  Are there any properties I need to change.

 

Thanks

2 replies

Oldest first
  1. 0
    Christine P ·

    sorry for the multiple posts,

    sorry for the multiple posts, my laptop was playing up

  2. 0
    Mike Testro ·

    Hi ChristineThe text in a

    Hi Christine

    The text in a user field only appears when there is a task on the gannt chart.

    My advice is to keep the data on a spreadsheet amd copy paste when needed in a programme.

    I will remove your surplus saves.

    Best regards

    Mike Testro