Importing Code Library Entries
- Created
- 2
- 5
Hi,
I'm currently trying to put together a template programme for a particular project where the data is being gathered in a rather cumbersome Excel document.
At the moment, I'm trying to build a code library so that I can make the transfer of data between Excel and Powerproject as painless as possible as there is a lot to group and sort (I'm hoping that I can create a suitable template to gather the data in the format that I want etc. etc.) but I digress....
What I would like to know is whether there is a way to import or paste multiple items into a code library rather than enter all the values manually?
I'm not concerned about setting bar formats as these will be determined by another code library but I have approximately 3000 items that I need to bring over which will be used to group and sort the programme. All of the items I need have already been entered into the spreadsheet so a simple copy and paste (if possible) would be ideal but I haven't had any success trying that with the code library.
Is this possible or can anyone suggest a method whereby I can paste this data straight into Powerproject as I would rather avoid adding 3000 items manually!
I primarily work in P6 due to client requirements so I may be missing something relatively simple but any advice or help would be very greatly appreciated!
I'm using version 12.0.02 if that makes any difference to what I'm attempting.
Many thanks in advance.
Ben
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?