Progress line on multiple tasks on same line
In the Open Standard
Mark McErleanMember for 14 years 5 months
- Created
- 3
- 2
0
Hi,
My firm uses a finishes programme for student accomodation, it goes 1st side stud & board, 1st fix M&E, 2nd side board etc. All of these tasks are on one line i.e. room 1. My problem rises when we have for example 90% 1st side board complete but at the same time may have 50% M&E complete also. I am unable to show progress on the second bar (the M&E) as we have not yet finished the 1 side stud & board.
Is there a way to show multiple progress lines easily (without overrowding the programme) or tell ASTA to show only the furthest date progressed?
Thanks