Planned / Actual % Complete S-Curve

Ryan WhealMember for 12 years
Created
4
4
0

Morning all,

 

Just trying to do a very basic planned vs actual percent complete S-Curve.


Any idea how it's done?

 

I just want to show the variations between the two.


Kind regards.

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RyanAsta software will do

    Hi Ryan

    Asta software will do this for you.

    Create a histogram with the selected data.

    Right click the histogram and select S-Curve - the graph will be created in Excell.

    Best regards

    Mike Testro

  2. 0
    Ryan Wheal ·

    Hi Mike, Thanks for your

    Hi Mike,

     

    Thanks for your response, but I'm struggling a little here.


    Any chance you can help me with a walkthrough of what I'm meant to do?

     

    This is the first histogram I've ever done and haven't a clue...


    Kind regards,

    Ryan

  3. 0
    Mike Testro ·

    Hi RyanThis is too big a

    Hi Ryan

    This is too big a topic for exchange here.

    Go to Help and search on Histograms.

    Select "Introduction to Histograms" and start from there.

    Best regards

    Mike Testro

  4. 0
    Ryan Wheal ·

    I don't want  to show any

    I don't want  to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.