Show Completed Task as Critical
In the Open Standard
Daniel StokerMember for 9 years 4 months
- Created
- 6
- 3
0
Hello,
I'm looking to analyse the critical path of a part-completed programme for a project, however, tasks that are 100% complete or have been progressed do not show up as critical.
Is there any way of showing progressed items as critical without having to remove the existing progress from each task?
Regards
Dan Stoker
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?