Skip to content

Show Completed Task as Critical

Daniel StokerMember for 9 years 4 months
Created
6
3
0

Hello,

I'm looking to analyse the critical path of a part-completed programme for a project, however, tasks that are 100% complete or have been progressed do not show up as critical.

Is there any way of showing progressed items as critical without having to remove the existing progress from each task?

Regards

Dan Stoker

6 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi DanielNoBest regardsMike

    Hi Daniel

    No

    Best regards

    Mike Testro

  2. 0
    Daniel Stoker ·

    Thanks Mike,I had thought as

    Thanks Mike,

    I had thought as much.

    Regards

    Dan Stoker

  3. 0
    Abbas Shakourifar ·

    Hi Daniel,An actual activity

    Hi Daniel,

    An actual activity cannot be critical by definition. However, there are different ways to "Show" something critical.

    If by showing you mean color "Red" follow these steps:

    - Make a user-defined code and select the activities which you like to show as critical.

    - On the Bar format table, Find the "Actual" Bar format, change your filter and make sure the coded activities are not included.

    - on the Bar format table, add a new one, use your code to filter the activities which you need to shown as critical and format them as"Red".

    I hope it helps.

    Abbas

  4. 0
    Trevor Rabey ·

    Daniel, the answer is "no"

    Daniel, the answer is "no" and the reason is the definition of "critical". The entire concept of the critical path method is only applicable to tasks which are planned/scheduled in the future. Once a task has an actual start date and an actual finish date, which of course must be in the past, then it's earliest and latest start and finish dates no longer exist, or rather, they must be the same as actual start date and actual finish date. I suspect that you are trying to find something called an "as built critical path", which is just a contradiction in terms. Any help?

  5. 0
    Daniel Stoker ·

    Thank you Abbas,That is a

    Thank you Abbas,

    That is a good way to visually demonstrate.

    Regards

    Dan

  6. 0
    Daniel Stoker ·

    Thanks Trevor,The

    Thanks Trevor,

    The contradictory critical path of the as built is essentially what I was looking for.

    Regards

    Dan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?