Is there a shortcut way of entering progress on ASTA?

Yasine AliMember for 11 years 2 months
Created
3
1
0

Hello everyone, 

I was wondering if there was a shortcut way of entering progress into ASTA activities.

I know that you can select the little box on the bottom corner and also use the mouse to drag percentage on the actual bar.

However I was wondering if there was a way where you could just click the bar and then enter a number on the keyboard for a % of how much has been completed.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Yasine - welcome to

    Hi Yasine - welcome to planning planet.

    Yes my method is very quick

    Set your progress percentages into a spreadsheet against each task.

    Make sure that the tasks on the Asta view are lined up with the spreadsheet - I do this by filtering the tasks with no restraints so only the tasks show.

    It is essential that they DO line up.

    Set up the chart progress column to show percent complete - save this as a view called progress entry.

    Make sure your progess period is set to the correct data date.

    Now copy / paste all the spreadsheet percent numbers into the progress column and reschedule - job done in 3 minutes max - even with 10,000 tasks.

    Give it a try.

    Best regards

    Mike Testro

  2. 0
    Yasine Ali ·

    Hi MikeThank you for thatJust

    Hi Mike

    Thank you for that

    Just tried it

    You have to use "paste values" instead of "paste" option

    Works a treat thanks!

  3. 0
    Farhad Khondaker ·

    Cheers guys, very helpful!

    Cheers guys, very helpful!