Skip to content

Baseline Vs Actual Progress in Line of Balance

Lo GaryMember for 16 years 8 months
Created
2
3
0

Dear,

 

Could we show both baseline and Actual Progress in the same Line of Balance, so that we could compare whether the progress is ahead or delay in Line of Balance?

 

 

Regards,

 

Gary Lo

Senior Project Mnager

2 replies

Oldest first
  1. 0
    Vipin lal ·

    Hai Gary,hope the question is

    Hai Gary,

    hope the question is how to show the base line and actual progress(ahead/delay) in the same time

    for that you have to

    1.Maintain the base line of the program 

    Project Menu>maintain Baseline>add>Save a copy of the current project

    2.Assign Baseline

    Project Menu>Project Baseline>''select your program''  and Primary Baseline>''select your program''

     

       Dont forget to tick the primary Baseline display options in the Bars in gantt chart

     

    Thanks

    VL

  2. 0
    Lo Gary ·

    Dear, The problem is whether

    Dear,

     

    The problem is whether this could be shown in Line of Balance rather than in Gannt Chart.

    Of course, this could be done in Gannt Chart.

     

    Thank!

     

    Regards,

     

    Gary Lo

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?