Microsoft Project, P6 to Asta Powerproject

Lo GaryMember for 16 years 8 months
Created
2
4
0

Dear,

My company usually use Microsoft Project and P6 to prepare programme. How could I export these prepared programme  to Asta Powerproject?

 

 

Regards,

 

Gary Lo

 

 

 

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi LoTo open MSP in

    Hi Lo

    To open MSP in powerproject save the file in MPX format.

    For P6 just open the P6 file directly from PowerProject software.

    To save the files just Save AS in the required format.

    You will lose a lot of the advanced Asta features - in version 13 of Asta you can make it look just like P6 anyway.

    Best regards

    Mike T.

  2. 0
    Ben Taunt ·

    Hi both,Just to confirm, the

    Hi both,

    Just to confirm, the supported Microsoft Project formats in Asta Powerproject are XML and MPP.  MPX was dropped by MS Project in verison 2000 I beleive so we have also now dropped support.

    To obtain support for openning and saving to MPP, you will also need MS Project installed on the same machine as Asta Powerproject.

    Cheers,

    Ben @ Asta Powerproject

Log in or join to reply