Good morning All,

I am trying to establish a KPI graph based on weekly activity count of the programme to display the progress of the project.

All I can do is resource the project and and create a histogram based on all resources and export the data to excel.

But I am sure there is another way (way easier and less time consuming) to reach weekly activity counts data and export to excel. I appreciate any  feed back may help.

Regards. 

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi TolgayIf you want to know

    Hi Tolgay

    If you want to know the number of tasks being worked on in any given week just progress the works and then filter on work in progress.

    Just add the number of tasks to your spreadsheet.

    Best regards

    Mike T.

  2. 0
    Ben Taunt ·

    You could also simply run a

    You could also simply run a time-slice filter...