Lags and type of duration format

Farhad KhondakerMember for 12 years
Created
1
2
0

Hi All,

Please can you advise on the following-

My programme activities are showing incosistent time units on my lags and slope. The activities are showing a mixture of seconds, minutes, hours and days on my activities.

Is there a way i can select a consistent format for all activities to have their lags calculated in days, weeks?

Thank you in advance.

 

Regards,

Farhad

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi FarhadIn the column you

    Hi Farhad

    In the column you can format the duration by the Format Cells dropdown.

    You can do the same by selectiong the link and change the suffix ie 15w or 15d.

    As a general rule you should only use lead lags for curing or drying out periods and then it should be set as calendar days - 15ed.

    Best regards

    Mike Testro