Overall vs Duration on Table Definition Dialog Box

Anu hansMember for 8 years 11 months
Created
5
3
0

I have created a column for Planned Percent Complete(PPC). When I opened the Table Definition Dialogue Box under Measure of Progress I can choose on drop down following options;

Duration

Overall

Cost

I'd like to know the difference when reporting progress between duration vs Overall please?

5 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,Applying Overall

    Hello,

    Applying Overall Progress to the summary tasks in the project means that Powerproject will calculate the completion % of the summary from the individual completion % of its subordinate tasks

    you can refer to the following page to better understand:

    https://help.elecosoft.com/powerproject/english/15.0.01/Content/HTML_Topics/Conceptual/Progress/Expanded_summary/Progoverall.htm?Highlight=overall%20progress

    Alexandre

  2. 0
    Anu hans ·

    Thanks lot for your

    Thanks lot for your explanation

  3. 0
    Sanjib Pradhan ·

    Source: Power Project Help:

    Source: Power Project Help: You may wish to enter and display progress as an overall percentage complete, a measurement that is independent of the duration of a task. For example, if a task is planned to take 10 days and 5 days have elapsed but only 20% of the task work has been done, you can record that the task is 20% overall complete, even though it is 50% complete when progress is viewed as a percentage of the task duration. Changes to the actual or remaining duration will not change the overall percentage complete value. Calculating progress in this way is most useful if you do not assign resources to your tasks. This progress is similar to P6 Physical Progress.
  4. 0
    Sanjib Pradhan ·

    Overall Progress :  You may

    Overall Progress :  You may wish to enter and display progress as an overall percentage complete, a measurement that is independent of the duration of a task. For example, if a task is planned to take 10 days and 5 days have elapsed but only 20% of the task work has been done, you can record that the task is 20% overall complete, even though it is 50% complete when progress is viewed as a percentage of the task duration. Changes to the actual or remaining duration will not change the overall percentage complete value. Calculating progress in this way is most useful if you do not assign resources to your tasks. This progress is similar to P6 Physical Progress.

     

    Sources : Power project help

  5. 0
    Anu hans ·

    Thanks lot

    Thanks lot

Log in or join to reply