Skip to content

How do you change duration default to days?

Dan HarangMember for 9 years 4 months
Created
1
2
0

Hello

I use Powerproject 12 and when I enter the duration for a task and hit enter it defaults to seconds. Is there a way to make the duration column default to days unless another unit is entered?

I've tried formating cells, catogory duration and the time unit day with out result.

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Dan - Welcome to planning

    Hi Dan - Welcome to planning plannet.

    Right Click on the top of the duration column.

    Select Table definition

    Select duration in the dropdown

    In the right hand panel find Overide Time Unit and select the one you want.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?