Skip to content

Issues with Total Float in Report

Daniel ZepkoMember for 9 years 3 months
Created
5
5
0

Ran a report to an excel file and ended up with really erroneous float on some activities.  for example, one activity indicates total float of 331d when the true total float in only 111d Start (August 17, 2017) late start (December 6, 2017) and Finish (September 16, 2017) and Late finish (December 18, 2017).

The erroneous float appears to be assinged to all activities on a (7) day clendars and just on the report as the correct float is indicated on the barchart view on the screen.

 

any suggestions would helpful

 

Dan

5 replies

Oldest first
  1. 0
    Mike Testro ·

    EmadThis is an Asta forum not

    Emad

    This is an Asta forum not P6.

    Daniel

    Float is always displayed in working days.

    You may be comparing the result with calendar (ed) days.

    Best regards

    Mike T.

  2. 0
    Emad Mofarej,PMP,PSP,CDT,CCM ·

    deleted

    deleted

  3. 0
    Daniel Zepko ·

    Again the float errors are

    Again the float errors are only for the Actvities assigned to a 7 day calendar .........while the correct float is indicated on screen but i get a different float when i run a report

  4. 0
    Mike Testro ·

    Hi DanielHow are you running

    Hi Daniel

    How are you running your report?

    Best regards

    Mike T.

  5. 0
    Rafael Davila ·

    Start Float cannot be greater

    Basic_Float_Calculations

    • Start Float cannot be greater than 111 days.
    • Finish Float cannot be greater than 93 days.

    Why 331d is still a mystery. It is a 3 to 1 ratio depending on time of day for start and finish dates. It might be the issue is within work patterns, perhaps an 8 h/d work pattern assigned to a 24 h/d calendar (?).  I do not use Asta PP but look for knowledge everywhere.  Work patterns is an interesting concept.

    Working with Asta PP Work Patterns 

    Work patterns on the same calendar are perhaps unique to Asta Power Project.  Work patterns look like applying multiple work weeks to different periods on same calendar, a special kind of calendar exception. This can be a common situation in some industries like Hospitals and Airlines.

    Its use can be transparent if when displaying calendar on calendar column you can also display work patterns: Calendar1(WP1,WP2,…).

    Two thumbs up to Asta Power Project.

    Availability of resources is not only defined by work hours but might also be by geographical location. I wonder how location patterns could be better implemented.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?