Weekly S curve for progress

Paul JonesMember for 9 years 4 months
Created
4
5
0
Hi- any know how to set weekly s curves for progress reporting? Thanks

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi PaulYou can set up any

    Hi Paul

    You can set up any histgrams comparing planned with actual with a multiple set of data.

    The graphs though are better presented on a spreadsheet when the data is exported.

    Best regards

    Mike Testro

  2. 0
    Paul Jones ·

    Thanks mike, is this done

    Thanks mike, is this done through the resource graphs set as cost centres?
  3. 0
    Mike Testro ·

    Hi PaulCan be cost but the

    Hi Paul

    Can be cost but the better measure is resource hours or even labour costs. days progress.

    Another is planned days progress over actual 

    Expenditure of cost is not a true reflection of progress.

    I call this the Golden Tap Syndrome - A gold tap costs 100 time a chrome one and takes the same time to fit.

    Best regards

    Mike T.

  4. 0
    Ben Taunt ·

    And don't forget the new "EVA

    And don't forget the new "EVA Reporter" export tool, which has superseded the older Progress Expert macro and is now included in all versions from 14 onwards...