Skip to content

Show Hammock allocation in a column at task level?

Richard MannMember for 10 years 6 months
Created
4
4
0

Hello,

I have a project on Asta that uses hammock tasks to summarise packages of work. I've been searching for a way to add a column that shows what hammock a task is assigned to; does anybody know if this is possible?

Any feedback would be greatly appreciated.

Thanks,

Rich

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RichardAssign a code to

    Hi Richard

    Assign a code to each task and then assign the same code to the hammock.

    Best regards

    Mike T.

  2. 0
    Richard Mann ·

    Thanks Mike, the only problem

    Thanks Mike, the only problem I have with that method is if I copy a task and it copies the code to the new task even though it's not allocated to the hammock of the original task. I wasn't sure if there was any other way of showing that the new task is not allocated to a hammock without doing it manually.

  3. 0
    Mike Testro ·

    Hi Richard.Just change the

    Hi Richard.

    Just change the code of the new task.

    Best regards

    Mike T.

  4. 0
    Charlotte Underhill ·

    Hi Richard,You can use the

    Hi Richard,

    You can use the parent name colun which is found under the identification category.

    Hope this helps :)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?