Critical Path - Help Needed
In the Open Standard
Dominic PlannerMember for 9 years 4 months
- Created
- 2
- 2
0
Good Morning,
I'm having issues establishing the Critical Path on my programme. I have a summary section at the top of my programme with Key Dates i.e. contract award, mobilisation, construction period, handover etc.
The Critical Path seems to bypass my entire programme and only link these activities as critical. The only 'Critical' items on the main programme is the start milestone and completion milestone.
Any help to get round this woul be appreciated.
Thanks