Default duration unit
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 2
- 3
0
Hello, Powerproject fanatics
Maybe the answer to my question is so obvious, however I was not able to find it
I want to enter the task duration in days; therfore I key in "5" for a task whose duration in "5 working days"
When I enter the duration of tasks in the spreadsheet, Powerproject always converts these 5 "days" into 5 "weeks", and displayes the value "25d" in the duration column.
Having looked everywhere in the dlalog boxes and the Online help, I cannot find my way.
Who will help me?
Thank you,
Alexandre
2 replies