Skip to content

Default duration unit

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
2
3
0

Hello, Powerproject fanatics

Maybe the answer to my question is so obvious, however I was not able to find it

I want to enter the task duration in days; therfore I key in "5" for a task whose duration in "5 working days"

When I enter the duration of tasks in the spreadsheet, Powerproject always converts these 5 "days" into 5 "weeks", and displayes the value "25d" in the duration column.

Having looked everywhere in the dlalog boxes and the Online help, I cannot find my way.

Who will help me?

Thank you,

Alexandre

2 replies

Oldest first
  1. 0
    Ben Taunt ·

    Hi Alexandre,On the View

    Hi Alexandre,

    On the View ribbon, you can change the default snapping unit in the drop down list:

     

     

    I just tested it and it is this field that controls what happens when you just tap "5" into the duration field on the spreadsheet.

    Thanks,

    Ben @ Powerproject

  2. 0
    Alexandre Faulx-Briole ·

    Hello BenThank you!Shame on

    Hello Ben

    Thank you!

    Shame on me, I should have found it by myself!

    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?