Float and dates don't nake sense
In the Open Standard
Catherine GrovesMember for 12 years 6 months
- Created
- 3
- 4
0
I have a schedule with a must finish by date of 6/24/21. The early finish for the project is 6/29/21, so about 5 days behind schedule. But it is showing -170 days of total float. I am not sure where this is computing from. The imposed finish is 6/24/2021 in properties. I have never had this happen before. Is there something I should at?
All my other projects are showing correct float. It is only this one.
Thanks
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?