Task duration depends on other task

M RooseboomMember for 23 years 8 months
Created
2
4
0
Hi,

I am using MS Project 2000 and am trying the following:

I have a task and I want to plan it based upon the duration of another task (testwork for example).

So task 1 takes 100 hours and task 2 takes 25% of task 1 (so 25 hours in this case)...

..I could first calculate it but when I change the first number I have to change it everywhere in the planning..

..is this possible?

Thx

2 replies

Oldest first
  1. 0
    Forum Guest ·
    I am faily certain that the function you are looking for is not an inbuilt function of Microsoft Project 2000.

    You could probably achieve something with a couple of milestones driven by successors with %lags and span them with a parent activity, but it would not be very elagant.

    Regards

    Paul E Harris
    Eastwood Harris Pty Ltd
  2. 0
    Ed van der Tak ·
    Beste M, Dear M,

    Altough were dutch, i will answer this in english. Best way to solve this problem is probably to set up a structure in which codes identify the related activities. In this way you can, after modifications to the schedule, run a macro to adjust related durations.

    Its not a common solution but were both seeking new and creative alternatives, I guess!

    Groeten,

    Ed van der Tak
    Aram Planning Consultants
    The Netherlands

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?