MSP Comment Line?

Bob DuncanMember for 22 years 7 months
Created
3
3
0
Hello,

I want to document 3 parallel projects with their own tasks.
And subdivide the 3 groups of tasks, then put a 1-line heading on-top of each group of tasks. So this will just be a text label and shouldn’t have a corresponding GANNT chart entry.

Is this possible?

Thanks,

Bob.

3 replies

Oldest first
  1. 0
    Will Russell ·
    No
  2. 0
    Paul Smith ·
    You could right click on the bar you do not wish to see & format it to have a blank shape. It will not then be visible.
  3. 0
    Will Russell ·
    Good idea, I hadn’t thought of that.
    You could mark or flag the lines that you don’t want a Gantt bar for and MSP will do it automatically for those "Tasks".

    Will