Displaying the % of the Baseline

Jon WardMember for 18 years 4 months
Created
11
3
0
help,,,

i have created a schedule with a baseline,, i have then used Number12 (re-named as Planned %) to detail the percentage of the Baseline,, the trouble is i’m getting 100% for all activities for the Planned % (Number 12),, even those activities that start and finish to the right of the data date line???
many thanks


IIf([Baseline Finish]<[Status Date] Or [Baseline Finish]=[Status Date],100,IIf([Baseline Start]>[Status Date],0,IIf([Baseline Start]<[Status Date] And [Baseline Finish]>[Status Date],ProjDateDiff([Baseline Start],[Status Date])/[Baseline Duration])*100))

11 replies

Oldest first
  1. 0
    Sreejith Nair ·
    Yep , I would like to call myself an expert in this:
    Here goes the formula :

    Planned % =IF((100/(Baseline_Finish_date-Baseline_Start_date+1)*(Date_Now-Baseline_Start_date+1))<0,0,IF((100/(Baseline_Finish_date-Baseline_Start_date+1)*(Date_Now-Baseline_Start_date+1))>100,100,(100/(Baseline_Finish_date-Baseline_Start_date+1)*(Date_Now-Baseline_Start_date+1))))

    I made this formula years back and still use deliberately in my trackers.(Excel based)

    If you need more info , please gimme a shout.

    Cheers ,

    Sreejith Nair
    Manager - Planning
    MG WLL
    Doha - Qatar
  2. 0
    Jon Ward ·
    thanks Sreejith,
    sorry to be thick but i keep getting an error on the code that reads Date_Now,, i have tried Status_Date,,
    any ideas?
  3. 0
    Sreejith Nair ·
    Use this formula in excel .. not in MSP
    replace Baseline_start ..etc by the respective cell numbers (H45, E35 ..etc)

    Read this post for more details:
    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=4&Top=46747

    Cheers!

    Sreejith
  4. 0
    Darren Kosa ·
    Jon,

    Just tried the formula in post #1 and it works fine for me. Have you checked your baseline and / or status date?

    Regards,

    Darren
  5. 0
    Darren Kosa ·
    Jon,

    Had another thought… have any of the activities moved to the right?

    Any delays in the schedule will not affect the planned % complete because that’s calculated from the Baseline Start / Finish Dates.

    In effect according to the baseline you should have completed the tasks so the Planned % Complete shows as 100%, but the activity hasn’t started yet so the % Complete shows 0%.

    Regards,

    Darren
  6. 0
    Sreejith Nair ·
    Hi!
    My formula is useful when you have the following info :
    Baseline start date
    Baseline finish date
    Current date/ Report date

    From these 3 parameters , my formula calculates planned physical %.

    If you have allocated a weighting / manhour to this activity you can get weighted progress / achieved manhour

    This can be used for generating progress S-Curve, Productivity curve or EVM stuff

    Cheers

    Sreejith
  7. 0
    Jon Ward ·
    here is what i’m trying to show, if line A is my activity bar, and is at 0%,, B is my base line bar (the verticle line is my date line,, so from that you can tell that the activity A has slipped to the right from the planned date,, so, i know how is show the % comp,, what i would like to show is the Planned % Complete,, in the example below the Planned % should read about 35%,, i have tried entering the formual (pasted at the bottom) in a new column (#12) in the formula section after i righ click on customise, however this does not tell me the % i’m looking for, i may be doing something obviolsy incorrect,, i would very much appreciate anyones help with this,, i know i shouldnt say this but P3 (once a Target has been created) details the baseline % quiet simply,, is there a method to check the data date of the baseline?

    A -----------
    B ----|-------

    IIf([Baseline Start]>[Status Date],0,IIf([Baseline Finish]<[Status Date],100,projdatediff([Status Date],[Baseline Start],IIf([Task Calendar]="None",[Project Calendar],[Task Calendar]))*100/projdatediff([Baseline Finish],[Baseline Start],IIf([Task Calendar]="None",[Project Calendar],[Task Calendar]))))
  8. 0
    Jon Ward ·
    ah rubbish,, in my example the line after A should be much further to the right,, well past B,, sorry HTML autoformats for us,,
  9. 0
    Darren Kosa ·
    Jon,

    Still can’t replicate your problem. Both formulae work fine in my test schedule.

    Sent you a PM to discuss.

    Regards,

    Darren
  10. 0
    Nassir Sh ·

    Dear friends,I need to

    Dear friends,

    I need to calculate the ""baseline"" and ""actual"" progress considering the weight factors of each activity.

    I have used John Ward's formula (of course it does not include the weight farctor). But I also got 100% progress for each activity, even for those that have not been started yet.

    can anyone help me with tis problem? and of course I need the formula to consider the weight factors as well...

    Thank you so much in advance...

  11. 0
    Nassir Sh ·

    Dear friends,I need to

    Dear friends,

    I need to calculate the ""baseline"" and ""actual"" progress considering the weight factors of each activity.

    I have used John Ward's formula (of course it does not include the weight farctor). But I also got 100% progress for each activity, even for those that have not been started yet.

    can anyone help me with tis problem? and of course I need the formula to consider the weight factors as well... Please keep in mind that I am absolutely new in MSP, so please let me  know exactly what I need to do step by step...

    Thank you so much in advance...