Progressing with MSP
In the Open Standard
Ronald FisherMember for 22 years 4 months
- Created
- 4
- 5
0
Hey guys. I am not a fan of MSP, but I am forced to use it. The problem I have is this. When progressing activities (not yet complete) the early finish date is calculated as being before the status date. What am I doing wrong, or is this a glitch in the software?
e.g. Actual start is 29/07. % Complete is 20%. Early finish is 13/11, and status date is 22/11
Anybody out there who can help, maybe persuade me that this software has any good uses.
e.g. Actual start is 29/07. % Complete is 20%. Early finish is 13/11, and status date is 22/11
Anybody out there who can help, maybe persuade me that this software has any good uses.