Progressing an Activity

Mark ChapmanMember for 20 years 5 months
Created
2
2
0
I must have got out of the bed the wrong side today as a simple task in Project is not so simple!

I have already moved the status date and now want to move an activity from being complete to not starting. I first reduced 100% to 0% and then dragged the activity to the RHS. This then picks up a "start no earlier than" although I change this to "start as soon as possible". This then returns back to the LHS presumably based on its logic.

Why is the activity stradling the status date? Calculation is on automatic.

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Mark,

    Select Tools-> Tracking-> Update Project on your Project Menu.
    Tick Reschedule uncompleted work to start after: (Data Date)
    Tick Entire Project then click Okay

    That should move all your remaining duration or uncompleted task start from data date.

    HTH
    Rodel
  2. 0
    Paul Harris ·
    Mark

    It would appear that you come from a conventional scheduling background where the end date of a task is calculated from the Data Date plus the Remaining Duration over the task or resource calendar.

    Rodel is correct in his statement, but MSP achieves this by splitting in progress task of applying an Early Start Constrain to unstarted tasks.

    Microsoft Project ignores the Status Date during normal recalculation. The end date of a task is calculated from the task Start Date plus the Duration.

    Basically, to hold a task “In Place” it must have either a Constraint, an Actual Start or a Predecessor. Removing an Early Start Constraint from a task in and in-progress schedule will send the task to the Start Date as MSP ignores the Status Date under normal scheduling conditions.

    There are several tools that you may wish to consider when progressing a schedule such as splitting a task etc, using the Tracking Toolbar, etc, etc, but bear in mind that MPS does not comply with generally accepted Critical Path rules when dealing with an in-progress schedule.

    Furthermore it takes me a lot longer to manage an in-progress task schedule in MSP than most other software I have used.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?