Saving Layouts
In the Open Standard
Philip RichardsMember for 22 years 9 months
- Created
- 4
- 4
0
Can anyoune advise regarding the possibility of saving layouts in MS Project.
I normally use P3, but have reluctantly agreed to run our present project in MS Project (The customer uses it and our installation sub contractor)
In P3 it is possible to set up Headers, Columns, Filters, Bars, print from/to dates etc and save any number of layouts within the project. Is there anything similar in MS Project. At the moment I am spending a lot of time re adjusting all the settings when I need to do a print.
I also have a problem, that when I insert an activity between two existing activities which are linked, MS Project automatically re sets the links to run through the new activity. Can this be swithed off?
Any help would be greatly appreciated.
I normally use P3, but have reluctantly agreed to run our present project in MS Project (The customer uses it and our installation sub contractor)
In P3 it is possible to set up Headers, Columns, Filters, Bars, print from/to dates etc and save any number of layouts within the project. Is there anything similar in MS Project. At the moment I am spending a lot of time re adjusting all the settings when I need to do a print.
I also have a problem, that when I insert an activity between two existing activities which are linked, MS Project automatically re sets the links to run through the new activity. Can this be swithed off?
Any help would be greatly appreciated.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?