Summary Tasks
In the Open Standard
Gerry MorganMember for 21 years 10 months
- Created
- 3
- 3
0
I know it is not correct to add resources to a summary task, but I am in a position where a project manager did do this and now there are actual hours also logged against the summary task.
The question is can they simply indent that summary task to become a regular task and insert a new summary task above it that can be kept clear of adding resources.
Is there anyway to stop someone from adding resources to a summary task in the first place?. and if actuals are logged against a summary task what happens to the schedule?.
Thanks GM
The question is can they simply indent that summary task to become a regular task and insert a new summary task above it that can be kept clear of adding resources.
Is there anyway to stop someone from adding resources to a summary task in the first place?. and if actuals are logged against a summary task what happens to the schedule?.
Thanks GM
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?