MS project - multiple project resource problems
In the Open Standard
J GMember for 21 years 2 months
- Created
- 9
- 5
0
Howdy,
Am newish to MS project, but can get my way around.
My problem is, that we have many individual projects that take 10-20 weeks long to complete Each of these projects are made up of many sub-contractors etc. On top of this, we ahve around 20 of these projects running in parrallel sharing the same resources.
I have set up a resource pool, and templated each of the projects, renamed them, and changed the appropriate details.
If i then decide to start all projects today, and then level out the plan for each of these projects, i am left with multiple unresolved resource allocation errors.
I have changed the priority of certain projects in an attempt to clear things up, ensured that all projects, and tasks are set to start as soon as possible, and removed any obvious problems with dependencies.
Still i am left with unresolved resource allocations. I know that i can manually move a few items, and start clearing things up, however this seems a little barbaric considering the reason we purchased MSproject 2003.
Any one have any ideas as to what is causing the unresolved errors? IS MSP going to solve my problems?
thanks.
Am newish to MS project, but can get my way around.
My problem is, that we have many individual projects that take 10-20 weeks long to complete Each of these projects are made up of many sub-contractors etc. On top of this, we ahve around 20 of these projects running in parrallel sharing the same resources.
I have set up a resource pool, and templated each of the projects, renamed them, and changed the appropriate details.
If i then decide to start all projects today, and then level out the plan for each of these projects, i am left with multiple unresolved resource allocation errors.
I have changed the priority of certain projects in an attempt to clear things up, ensured that all projects, and tasks are set to start as soon as possible, and removed any obvious problems with dependencies.
Still i am left with unresolved resource allocations. I know that i can manually move a few items, and start clearing things up, however this seems a little barbaric considering the reason we purchased MSproject 2003.
Any one have any ideas as to what is causing the unresolved errors? IS MSP going to solve my problems?
thanks.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?