Resource Overallocation/Fixed Work Query
In the Open Standard
Neil GartlandMember for 16 years 7 months
- Created
- 13
- 5
0
I have 3 tasks in a project each consisting of 20h work, set to be fixed work scheduled over a 5 day duration starting and finishing at the same time. All three tasks are allocated to the same resource, so MS Project allocates 50% of the user’s time to each task by default. The means that the resource is 150% allocated.
Is there any way to automatically resolve this resource over allocation in this case by MS Project reducing the % allocation to 33% and extending the duration of the task.
Any help would be really appreciated
Is there any way to automatically resolve this resource over allocation in this case by MS Project reducing the % allocation to 33% and extending the duration of the task.
Any help would be really appreciated
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?