Mary JoAnn
Displaying the progress as remaining duration in P3 and SureTrak shows progress from the Actual Start to the Data Date. This is not an inbuilt function of MSP.
MSP will show progress by default as % Complete only.
One can programme MSP to show the RD bar by using Finish1 on each task to represent the Data Date. Then setting Finish1 to the Status date by using a formula Tools, Customize, Fields form. Then reformatting the Progress bar to span from Actual Start to Finish1. There is no option to span a bar from Actual Start to Status date.
PS. Don’t forget to set the status date.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au