Retriving reports from Custom fields

Joseph JesudossMember for 21 years 2 months
Created
1
29
0
I have included custom field (Values: Operating, Capital) in my task page. I am trying to get report only for capital or operating projects. I can only have filter option in the view, I know where I can get filtered result.
In the report functions (custom reports) in the filter option there is no custom field listed. I just want to know how to filter the custom fields in report functions?

1 reply

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Go to:
    1) Filter > create a new filter using custom fields that you have created.
    2) Custom Reports > create a new report > definition tab and choose the filter.

    Now you can get the report you have desired.

    HTH.

Log in or join to reply